Churngold were contracted to work with Keepmoat Regeneration, to install all associated infrastructure including deep drainage, Pre-cast outfalls, retaining structures including a large concrete attenuation pond for the commencement of the construction of 222 houses and 6 apartment blocks.
The main bulk of works was the new access road that runs parallel to the River Usk, large Gabion baskets where installed to retain the different in levels on a partially contaminated site.
All works were undertaken next to a capped tip, and a fully tanked attenuation pond was formed to provide a means to attenuate potential flood waters.
Churngold used their nationally renowned experience in delivering the full range of Groundworks solutions to deliver the following works:
Cut and Fill optimisation
Piling Matt installation
Retaining Structures – Brickwork
Retaining Structures – Gabion baskets
Adoptable Storm and Foul system & connections
Large Concrete Attenuation Pond
Linear drainage
278 & Section 38 Highways Works
Surfacing
New ducting and services
Contaminated Land
Poor Ground conditions
Tidal groundwater within Drainage
Existing Services
Service Connections