HMP Channings Wood

66 weeks


Project Overview

Client: Kier Construction

Project Name: HMP Channings Wood

Location: Newton Abbott

Sector: Custodial

Project Value: £18M

Project Period: 66 weeks

The Project is to expand Channings Wood Prison creating an additional 494 prison places and 15 new associated ancillary buildings. The additional prisoners will be housed within two new T60 blocks.

The site is complex featuring a large existing prison, live services, excavating rock, working with prison staff, testing and disposal of contaminated ground, all in line with our environmental and sustainability obligations.

The project was fast-tracked by MoJ and Kier, meaning proactive design development and management was vital and a key client requirement.

Churngold excel in assisting their clients with this challenge.

Subcontract works undertaken

  • Pile attendance

  • Pile cropping ODEX piles

  • Pile caps 

  • Drainage

  • Water / gas proofing

  • Services installation

  • Large Attenuation tank install

  • Kerb Laying

  • Tarmac surfacing

Churngold successfully managed 

  • Fast paced design development

  • Working within a live prison

  • Meeting programme expectations

  • EL1 security clearance for over 100 personnel

  • Constructing new vehicle airlock

  • Excavating, crushing and reusing 1000’s of tons of rock enhancing the project’s sustainability credentials

  • Excavating around a multitude of existing services